Coast Guard Cover Up

The Sand dredging project has reached the Coast Guard Station at the west end of Gilgo State Park and the cover up is in progress. Pictures below are from end of day Jamuary 9th and midday, January 10th.

View looking east from the entrance to Gilgo State Park.
View looking east from the entrance to Gilgo State Park at Coast Guard.
Coast Guard 1/10/19
View looking Southeast from the west side of Gilgo State Park at Coast Guard.
Looking East from the Breach at Coast Guard
Looking east at the Coast Guard Station disappearing under the dredged sand.

The slide show above shows Coast Guard Station from the morning to evening dredging operations on January 10th, 2019. The rest of the photos are of the Coast Guard Station on the 11th to the 17th of January. The pictures were taken from the top of the path to the beach at the east end of Cottage Walk.

Development West of Cedar

Its the Bergen Outfall Pipe Upgrade!

Press release from the company awarded project.

OHL USA, Inc., an OHL North America company, announces it has been awarded a $187 million joint venture contract (40% OHL USA, Inc., 40% Posillico Civil, Inc., 20% SELI Overseas USA, Inc.) by Suffolk County Department of Public Works to replace existing outfall pipe at the Bergen Point Waste Water Treatment Plant (WWTP) in Babylon, NY. This is the largest construction project in Suffolk County in several decades and OHL’s first project on Long Island, expanding OHL’s regional presence in the New York area. Construction started on February 8th, 2018 and will be completed by summer 2021.

Just west of Cedar Beach, the staging area for the sewer pipe upgrade.
Just west of Cedar Beach, the staging area for the sewer pipe upgrade.

The project includes the construction of a ​14,200-foot, 120-inch
inner diameter tunnel through a mixture of soft soil materials under the
Great South Bay with the use of a tunnel boring machine (TBM). The
tunnel will be constructed to replace the existing Prestressed Concrete
Cylinder Pipe (PCCP) outfall pipe, which carries
millions of gallons of treated wastewater, connecting the Bergen Point
Wastewater Treatment Plant (WWTP) to the Barrier Island under the Great
South Bay. The new tunnel will address the concerns of potential failure
of the current pipe and has a longer lifespan.

Bergen Point Pipe Replacement Project
View looking north of the Bergen Point Pipe Replacement Project at Cedar Beach

The tunnel will be excavated and concurrently lined using precast
concrete segment rings. The JV has selected a slurry TBM as the most
effective and efficient means of tunnel excavation and elected to use
48-inch wide precast segment liners. The shaft construction will be
divided into major work phases including site preparation, excavation of
the launch shaft and installation of the new slurry TBM. Once the TBM
is installed, tunnel excavation will proceed in four foot “pushes,”
followed by the installation of the permanent tunnel lining.
Additionally, the team will also complete ancillary work within the
tunnel including the installation of new piping and valving, associated
plumbing, HVAC, and electrical work.

Beach Blanket Bingo

There is going to be room to play!!

Dredging of Fire Island Inlet is in progress! This multi-purpose project provides a navigation channel and storm benefits through the dredging of the navigation channel with all the dredged sand placed westward along Gilgo Beach shoreline.

The sand replenishment project is making good progress with the beach filled in from the Sore Thumb to past Hemlock Cove as of today’s posting.

The Project involved moving 2.1 million cubic yards of sand from the Fire Island Inlet to the Town of Babylon and New York State Gilgo Beach areas to the west. The minimum depth of the navigation channel thru the inlet is to be 14 feet. The new beach is projected to be an average beach of 100 feet. The cost of the project is 26.2 million dollars and should be completed by April 10th, 2019.

Above is slide show photographed on December 27th, 2018, of the walk from the path at end of Cottage Walk walking east to the beach area where the erosion is the worst. Thank God the Dredging Project is less than a mile away.

Dredging front of Coast Guard Dove Dec 2018
Dredging front of Coast Guard Cove Dec 2018

For the Coast Guard Station area of beach, the sand replenishment project is just in a nick of time. Last week with the 40 mph on shore winds, cars on Ocean Parkway were treated to a 20 foot high sea foam funnel blowing across the highway at dusk. Take a look at the pictures below of the dune line just west of Coast Guard, one more good storm might have breached the dune line.

Dunes 100' east path at end Cottage Walk looking north, this is the most eroded location
Dunes 100′ east path at end Cottage Walk looking north, this is the most eroded location
Dunes 100' east path at end Cottage Walk around 4 feet high. Dec 2018
Dunes 100′ east path at end Cottage Walk around 4 feet high. Dec 2018
Close up of Dune 100' east path at end Cottage Walk looking north from base of dune! You can see Ocean Parkway.
Close up of Dune 100′ east path at end Cottage Walk looking north from base of dune!
Dunes 100′ east path at end Cottage Walk looking north at Car on Ocean Parkway.

the Farmer’s Market

Check out the new Farmers Market in the Oak Beach Parking lot this Saturday!

Local venders offering quality organic and home grown produce and things.

Stop on by Saturday June 30th!

Kayaking for our Veterans

On September 16th, the Town of Babylon hosts the 3rd annual Kayaking for a Cause event at Cedar Beach to Benefit our Veterans, here are the specifics from the Town of Babylons web site.

This year’s event will go towards helping the VFW Warren Keer Post 9482 in Copiague.

Registration begins at 7:30 AM, with 1st launch at 9:00 AM.
the Cause offers 3 skill level of trails, so whether your a beginner or pro, we have a route for you.

* * New in 2018, SUP’s are Welcome to join in the Cause!

So PUT September 16th on your calender and join the Cause!

Dune Breach Close May 2018

In the last couple of months a breach of the dune line just west of Coast Guard is working its way to Ocean Parkway. As you can see, the ocean has eaten thru a major portion of the dune structure for about 50 feet of dunes.